Current Participants

Current Pool Participant might deregister their Production Facility from the Market by applying for deregistration as per the Market Rules.   

A registered participant in the Oman Electricity Spot market can apply to deregister their Production Facility from the market.

Basis for Deregistration:

  • Where a Registered Production Facility is not or ceases to be required to Participate in the Pool, the Generator may Deregister the Production Facility.
  • Where a Registered Production Facility is not or ceases to be entitled to Participate in the Pool, the Generator shall Deregister the Production Facility.
  • Where the Party which is Registered ceases to be the Generator in relation to a Production Facility, that Party shall Deregister the Production Facility (and the Party who is Generator shall Register it), unless those Parties and the Market Operator agree on a different process.
  • Where a Party is required to Deregister a Production Facility, the Party shall take the required steps in accordance with the Market Rules to Deregister the Production Facility with effect from or as soon as practicable after the time from which the requirement exists.
  • For the purposes of section b above, the circumstances in which a Production Facility is not or ceases to be entitled to Participate in the Pool include (without limitation) that the requirements in the Market Rules are not or cease to be satisfied, unless the Authority has given and not withdrawn a contrary direction to the Market Operator.
  • Where any change occurs in relation to a Production Facility (including any GenSet or GenSets ceasing to be part of a Production Facility or to be Connected) which does not result in the Production Facility ceasing to Participate in the Pool, such change shall be recorded as a change in Registration in accordance with the Market Rules and not by Deregistration.

Where a Party wishes or is required to Deregister a Production Facility, the Party shall apply for Deregistration by submitting to the Market Operator the following details:

  • the Production Facility ID;
  • the date with effect from which the Production Facility is to be Deregistered;
  • the grounds on which the Party wishes or is required to Deregister the Production Facility.
  • validate the application by reviewing and confirming the grounds for the Deregistration;
  • if the Market Operator considers that the application to Deregister is not valid, so inform the applying Party, and discuss with that Party with a view to resolving the matter;
  • if the Market Operator is satisfied that the application is valid, remove the Production Facility from the Market Register in accordance with the application;
  • notify the Deregistration to the applying Party, each other Party and the Authority.

With effect from the Deregistration of a Production Facility, the Production Facility shall cease (if it has not already ceased) to Participate in the Pool.

The Deregistration of a Production Facility does not affect the rights or obligations of any Party under the Market Rules in relation to the Production Facility, and has no other effect in respect of Settlement, Trading or payment of Pool Charges, in respect of any Trading Day prior to the day on which the Deregistration is effective.

To re-register, the Applicant must complete all registration process required for a new Participant.